A2300 scheme: capital allocation and authority to submit business case and award contract

The Department for Transport (DfT) has provided funding from the Local Growth Fund to assist with the design and development of a full business case for the A2300 scheme following the submission of an outline business case by the County Council in June 2018 (decision HI03 18/19). The same decision delegated authority to the Director of Highways & Transport to tender, procure and award the services of Design & Build and Contract Administration from the approved list of contractors on the Highways and Transport Frameworks.

 

In November 2018, the Director of Highways and Transport awarded the design contract to Jackson Civil Engineering Limited (decision OKD13 18/19) which enabled a detailed design for the scheme to be completed and the development of a full business case.

 

The submission and approval of the full business case will enable the remaining LGF to be secured from the DfT as a contribution towards the construction of the scheme.

Decision type: Key

Reason Key: Expenditure > £500,000;

Decision status: Recommendations Approved

Divisions affected: Hurstpierpoint & Bolney;

Notice of proposed decision first published: 24/04/2019

Decision due: June 2019 by Cabinet Member for Highways and Infrastructure

Lead member: Councillor Roger Elkins roger.elkins@westsussex.gov.uk

Contact: Hiong Ching Hii, Project Manager Email: hiongching.hii@westsussex.gov.uk Tel: 033 022 22636.

Consultation process

Representations concerning this proposed decision can be made to the Cabinet Member for Highways and Infrastructure, via the officer contact, by the beginning of the month in which the decision is due to be taken.

 

Consultees

Public engagement was undertaken in autumn 2018 and the outcome was published on 1 March 2019.

 