Award of Contract for the expansion of Bourne Community College

Due to the need to provide additional places at Bourne Community College the Cabinet Member for Education and Skills took a decision during December 2018 (Decision ref ES14 (18/19)) to approve the allocation of £3.674m from the Basic Need Capital Programme to fund expansion works at Bourne Community College to increase its admission number in September 2019 from 150 pupils in each year group to 180 pupils in each year group As part of the decision the Cabinet Member delegated authority to the Executive Director Economy, Infrastructure and Environment to award the contract to carry out the necessary works.

 

Following receipt of the Stage 2 tender sum, it became apparent that the gross approved budget was inadequate for the works as designed. This deficiency in the budget was dealt with through a change request, in accordance with the capital programme governance process.

 

Decision type: Key

Reason Key: Expenditure > £500,000;

Decision status: Recommendations Approved

Divisions affected: Bourne;

Notice of proposed decision first published: 17/04/2018

Decision due: March 2019 by Executive Director Economy, Infrastructure and Environment

Lead member: Lee Harris, Director of Place Services lee.harris@westsussex.gov.uk

Contact: Philippa Hind, Head of Development (Acting) Email: philippa.hind@westsussex.gov.uk Tel: 033 022 23041.

Consultation process

Representations concerning this proposed decision can be made to the Executive Director Economy, Infrastructure and Environment, via the officer contact, by the beginning of the month in which the decision is due to be taken.

Democratic Services Contact: Wendy Saunders Tel: 033 022 22553