The Halewick Lane Battery Storage project proposes the re-development of the previously derelict North Sompting Waste Management Site into an income generating battery storage project.
The Cabinet Member for Environment delegated authority to the Director of Environment and Public Protection to approve the design and build contract award.
When the procurement process has concluded, the Director of Environment and Public Protection will be asked to award the design and build contract.
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: For Determination
Divisions affected: Sompting & North Lancing;
Notice of proposed decision first published: 19/08/2021
Decision due: February 2022 by Director of Environment and Public Protection
Lead member: Steve Read, Assistant Director (Environment and Public Protection) steve.read@westsussex.gov.uk
Contact: David Robinson Email: david.robinson@westsussex.gov.uk Tel: 033 022 26995.
Consultation process
Representations concerning this proposed decision can be made to the Director of Environment and Public Protection, via the officer contact, by the beginning of the month in which the decision is due to be taken.
Consultees
Director of Law and Assurance
Director of Finance and Support Services
Democratic Services Contact: Judith Shore Tel: 033 022 26052