Issue details
Award of contract for grid connection cabling works at the Halewick Lane Battery Storage project
The Halewick Lane Battery Storage project proposes the re-development of the previously derelict North Sompting Waste Management Site into an income generating battery storage project. In an earlier phase of work the site was cleared of derelict buildings and prepared for installation of the new infrastructure.
The Cabinet Member for Environment and Climate Change delegated authority to the Director of Environment and Public Protection to commence procurement for and to award a grid connection cabling contract. The procurement process has now concluded, and the Director will be asked to award the contract for the cabling works to join the Halewick Lane site to the Worthing grid.
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: Recommendations Approved
Divisions affected: Sompting & North Lancing;
Notice of proposed decision first published: 28/05/2021
Decision due: July 2021 by Director of Environment and Public Protection
Lead member: Steve Read, Assistant Director (Environment and Public Protection) steve.read@westsussex.gov.uk
Contact: Tom Coates, Senior Adviser Email: tom.coates@westsussex.gov.uk Tel: 033 022 26458.
Consultation process
Representations concerning this proposed decision can be made to the Director of Environment and Public Protection, via the officer contact, by the beginning of the month in which the decision is due to be taken.
Consultees
Director of Law and Assurance
Director of Finance and Support Services
Democratic Services Contact: Judith Shore Tel: 033 022 26052
Decisions
Background papers
- None