Issue details

Award of contract for grid connection cabling works at the Halewick Lane Battery Storage project

The Halewick Lane Battery Storage project proposes the re-development of the previously derelict North Sompting Waste Management Site into an income generating battery storage project. In an earlier phase of work the site was cleared of derelict buildings and prepared for installation of the new infrastructure.

 

The Cabinet Member for Environment and Climate Change delegated authority to the Director of Environment and Public Protection to commence procurement for and to award a grid connection cabling contract. The procurement process has now concluded, and the Director will be asked to award the contract for the cabling works to join the Halewick Lane site to the Worthing grid.

 

Decision type: Key

Reason Key: Expenditure > £500,000;

Decision status: Recommendations Approved

Divisions affected: Sompting & North Lancing;

Notice of proposed decision first published: 28/05/2021

Decision due: July 2021 by Director of Environment and Public Protection

Lead member: Steve Read, Assistant Director (Environment and Public Protection) steve.read@westsussex.gov.uk

Contact: Tom Coates, Senior Adviser Email: tom.coates@westsussex.gov.uk Tel: 033 022 26458.

Consultation process

Representations concerning this proposed decision can be made to the Director of Environment and Public Protection, via the officer contact, by the beginning of the month in which the decision is due to be taken.

 

Consultees

Director of Law and Assurance

Director of Finance and Support Services

Democratic Services Contact: Judith Shore Tel: 033 022 26052

Decisions

Background papers

  • None