Issue details
Budget Increase: Crawley Growth Programme Eastern Gateway Scheme
The Eastern Gateway scheme is a key project within the growth programme and seeks to improve connectivity between the town and key development sites in the vicinity of the proposals including the Town Hall, County Buildings, Crawley College and Telford Place. In February 2019, the Executive Director approved the commencement of the tender process to secure a design and build Contractor through the WSCC Highways Design and Build framework. The design contract (stage 1) was awarded to Volker Fitzpatrick.
Design fees were allocated to each Crawley growth programme project. A design budget increase is required of £800k from within the Eastern gateway allocation of £8.35m. The eastern gateway allocation of £8.35m remains unchanged but the increase in design budget is required to:
- Undertake further redesign works, accommodate the new town hall schemes interface (Estimated design fee and project management cost are £380k).
- Complete liaison work with the utility providers.
The Executive Director Place Services will be asked, prior to the award of the construction contract, to increase the Design Budget.
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: For Determination
Divisions affected: Northgate & West Green;
Notice of proposed decision first published: 15/02/2021
Decision due: March 2021 by Executive Director Place Services
Lead member: Lee Harris, Director of Place Services lee.harris@westsussex.gov.uk
Contact: Marie Ovenden, Acting Head of Service - Migration and Resettlement Service Email: marie.ovenden@westsussex.gov.uk Tel: 033 022 23854.
Consultation process
Representation can be made in the month before that in which the decision is due to be taken.
Consultees
Crawley Growth Board
Democratic Services Contact: Suzannah Hill Tel. 033 022 22551
Background3: A Prosperous Place
Background papers
- None