Contract award: A24 Robin Hood Roundabout Improvement

The West of Horsham highway infrastructure package includes four significant highway junction projects to support the delivery of the major housing and employment allocations to the east and west of the A24 as follows -

 

• A24 Farthings Hill roundabout (completed 2020)

• A281 Newbridge roundabout (completed 2020)

• A24 Great Daux roundabout (on hold)

• A24 Robin Hood roundabout (see below)

 

In July 2020, the Cabinet Member for Highways and Infrastructure approved the commencement of the procurement process to secure a build contractor for the A24 Robin Hood scheme and delegated authority to the Director of Highways, Transport and Planning to appoint the build contractor.

 

The procurement process has now concluded.

 

Decision type: Key

Reason Key: Expenditure > £500,000;

Decision status: Recommendations Approved

Divisions affected: Broadbridge; Holbrook; Hurstpierpoint & Bolney;

Notice of proposed decision first published: 22/10/2020

Decision due: January 2021 by Director of Highways, Transport and Planning

Lead member: Matt Davey, Assistant Director (Highways, Transport and Planning) matt.davey@westsussex.gov.uk

Contact: Stephen Reed, Major Projects Officer Email: stephen.reed@westsussex.gov.uk Tel: 033 022 27328.

Consultation process

Representations concerning this proposed decision can be made to the Director of Highways, Transport and Planning, via the officer contact, by the beginning of the month in which the decision is due to be taken.

 

Consultees

Local Members

Horsham District Council

Local Parish Councils (Warnham, Slinfold, Itchingford)

 

Democratic Services Contact: Judith Shore Tel: 033 022 26052

Background3: A Prosperous Place

Decisions

Background papers

  • None