Issue details

Award of Contract Partial Demolition Crawley County Buildings OKD49 20 /21

In August 2017 the Leader approved the Crawley Growth Programme LDR04 17.18 and following approval of the business case by the West Sussex Local Enterprise Partnership, delegated authority to the (then entitled) Executive Director Economy, Infrastructure and Environment to progress the projects. Crawley County Buildings partial demolition is a key project within the growth programme.

 

A full demolition was approved in July 2019. As set out in the report a change request was submitted in March 2020 to reduce the full demolition to a partial demolition.

 

 

Decision type: Key

Reason Key: Expenditure > £500,000;

Decision status: Recommendations Approved

Divisions affected: Northgate & West Green;

Notice of proposed decision first published: 01/09/2020

Decision due: December 2020 by Executive Director Place Services

Lead director: Lee Harris

Contact: Marie Ovenden, Acting Head of Service - Migration and Resettlement Service Email: marie.ovenden@westsussex.gov.uk Tel: 033 022 23854.

Consultation process

Representation can be made via the officer contact in the month prior to that in which the decision is to be taken.

Consultees

Crawley Growth programme Growth board; Crawley OPE programme team; Current occupiers of Centenary House, Crawley.

Democratic Services Contact: Suzannah Hill Tel. 033 022 22551

Background3: Prosperous Place

Decisions

Background papers

  • none