Award of Contract and Endorsement of Fund Allocation: Crawley Growth Programme Eastern Gateway Scheme OKD73 20-21

18/05/2021 - Award of Contract and Endorsement of Fund Allocation: Crawley Growth Programme Eastern Gateway Scheme OKD73 20-21

1.   The Executive Director for Place Services has approved the allocation of the remaining unspent project budget of £7.360m to complete construction. This includes an allocation of up to £0.500k for this project, from within the Crawley Growth programme capital allocation to increase Eastern Gateway’s total budget from a total of £8.350m to a total £8.850m; and

2.   approved the award of the Phase 2 contract (the construction phase) to Volker Fitzpatrick Limited and endorses that the Contract Target Price is within the above remaining budget constraint of £7.360m.