Burgess Hill Growth Programme - Approval of Place and Connectivity Programme Funding Agreement

20/03/2019 - Burgess Hill Growth Programme - Approval of Place and Connectivity Programme Funding Agreement - LDR09(18.19)

The Leader has approved:

 

(1)     That WSCC agree to act as the Delivery Body for the Burgess Hill and Connectivity Programme and authority be given to the Director of Law and Assurance to complete the associated funding agreement on behalf of the Council.

 

(2)     That the Capital Programme be updated to include the £15.002m of schemes and associated external funding for which WSCC are identified as the Contractual Lead for scheme design and delivery.

 

(3)     That the governance arrangements as set out at Appendix A be approved, noting the flexibilities that apply regarding the reallocation of available external funds within the programme, and subject to no call arising on the Council’s core capital funding.

 

(4)     That subject to those governance arrangements being applied, including the establishment development of scheme business cases, the Executive Director of Economy, Infrastructure and Environment be granted delegated authority to progress the projects within the programme to completion.