4.1 The Committee considered the
Audit Result Reports by the External Auditor EY (copies appended to
the signed minutes).
4.2 Mrs Thompson (EY) began by
thanking officers for their prompt work during the accounts
audit. The audit had been smooth as a
result of this and the accounts were in a good place.
4.3 The Committee agreed to focus on
the West Sussex County Council Statement audit first.
4.3 Mrs Thompson outlined the key
work that had taken place including the work required to reflect
the change in portfolios which had led to a change in audit scope
and so an additional fee had been included. There had also been a change in materiality levels
which had led to an updated threshold for reporting misstatements
of £1.3m.
4.4 It was explained that there was
outstanding work related to the Whole of Government Accounts
submission. The deadline for this was
the end of August, but it was confirmed that this did not affect
the audit.
4.5 There were no adjusted
misstatements to highlight and it was proposed that an unqualified
opinion would be given on the accounts.
4.6 Mr Mathers (EY) reported that a
risk had been identified for management override. This had been investigated and no evidence of
management override was found. A main
focus of the audit had been on land and building valuation which
had found a potentially material difference. Additional work was undertaken to
investigate. This work showed that no
changes were ultimately required.
4.7 Mr Mathers reported that all
recommended adjustments arising from the audit had been made or, in
the case of the PFI recommendations that had been reported later,
would be made in the 2018/19 accounts.
4.8 Mr Mathers reported on value for money
(VFM) risks and the two areas that had
been identified; weakness in procurement and contract management,
and financial resilience. Improved
commissioning activity had been seen for Adult services, but there
is still work to do. Childrens’ Services represented a high cost
pressure and work is still required. A
holistic approach had been recommended to ensure good working with
other parties. In terms of financial
resilience, slippage within the capital programme had been
identified which officers were addressing. There was appropriate monitoring of the Medium
Term Financial Strategy. Overall EY
were satisfied with arrangements and an unqualified VFM conclusion
was proposed.
4.9 The Chairman thanked EY and
officers for their hard work in preparing the accounts in time for
the new deadline.
4.10 The Committee made comments including those
that follow.
- Sought clarity on the difference in materiality on the Property,
Plant and Equipment (PPE) revaluation issue. – Mr Mathers explained
that the £44m related to
EY’s estimate of the difference between the carrying value
and the current value of PPE assets that are not subject to
revaluation, which if the council had adopted to index the assets
which had not been valued in the year, would have resulted in an
increase of the carrying value of PPE. The internal
valuation specialist within EY reported that the County
Council’s approach was reasonable.
- Asked if the
Committee could request that items were revalued outside of the
five year cycle. – Mr
Mathers reported that it was the County Council’s judgement
over what was included in the valuation. It was thought that the County Council’s
approach was sensible as it covered a good sample and allowed for
further investigation if required.
- Questioned if
certain asset types could be revalued at different times, and if
the valuation included unrealised assets such as
infrastructure. – Mr
Mathers explained that CIPFA stated what assets should be valued
over a 5 year cycle with sufficient work performed to ensure no
material misstatement in any one year.
The County Council undertook an annual impairment review to look at
specific assets. All PPE had been
included. Short life assets such as
vehicles were not included.
- Queried why the
Schools PFI had looked back to 2009/10.
– Mr Mathers explained that this was due to a
review of the accounting changes which came in in
2009/10. Some residual differences had
been identified in the 2016/17 audit but had not been amended as
they were not material. These
differences were highlighted this year by the EY specialist at a
very late stage of the audit.
- Requested an
explanation on the difference in the capital budget from the
outturn. – Ms
Eberhart explained that the difference was linked to a refresh of
the capital programme and the identification of underspends and
delays to projects. The Performance and
Finance Select Committee (PFSC) had looked into this and were
satisfied with the explanation. Mr Hunt
clarified that the issues were linked to factors outside of the
County Council’s control. A good
team were in place to work on this with assistance from a
multi-disciplinary partner.
- Queried if the
process for commissioning was too complex and sought guidance on
best practice. – Mrs
Thompson explained that commissioning was a key action, and a
challenge for all councils to comply with best
practice. A review had been undertaken
to give assurance on the Council’s arrangements. More work was required and recognised by the
County Council within the Annual Governance Statement.
- Sought clarity on
the process for the Target Operating Model (TOM). – Ms Eberhart explained that
PFSC had set up the Contracts Task and Finish Group which had
looked into the TOM. The PFSC report
outlined the details of the procurement cycle, and the new
organisational structure was out for consultation. Ms Eberhart agreed to circulate slides on
this.
4.11 The
Committee then considered the West Sussex Pension Fund
statement.
4.12 Mrs
Thompson introduced the report and explained that there were no
areas of outstanding work. Mr Mathers
reported that there were significant risks of management override
that EY would seek assurance that the grounds for this were
appropriately managed. There were no
specific areas that required bringing to the Committee’s
attention.
4.13 The Committee made
comments including those that follow.
- Queried the
project to reduce the differences in membership numbers. – Mr Hunt explained that the
pension administration transfer was in train and would address
this. Mrs Davies (Finance Manager
– Pension Fund (Accounting & Reporting)) explained that
officers were working with Capita and employers to resolve
differences in active membership. An
incorrect report had been received from Capita- HRMI and so the
Pension Fund had to produce the correct report. Mr Mathers explained that this had been a new
process to reconcile pensions paid at a member level.
-
Concerns were raised on the transfer
of erroneous data and reassurance was sought that this would be
corrected. – Ms
Eberhart stressed the importance of the transfer project and gave
reassurance that officers were working with Capita and Hampshire
County Council to ensure clean, reconciled data is uploaded onto
the Hampshire County Council system.
Work on the reconciliation would be completed and correct for the
triennial valuation. The Committee
agreed to write to the Pensions Panel Chairman to request
reassurance on this process. Mrs
Thompson confirmed that this was a focus for EY. Mr O’Brennan (Principal Pensions Accountant)
explained that officers completed an annual reconciliation of the
data to highlight and correct errors.
4.13 Resolved – That the Committee notes the audit result reports
from EY for West Sussex County Council and the West Sussex Pension
Fund.