A259 Littlehampton Corridor Improvements HI09 (19/20)

Decision Maker: Cabinet Member for Highways and Infrastructure

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The A259 Littlehampton Corridor improvement scheme comprises dualling the existing single carriageway between the new Fitzalan Link Road (east of the Wick Roundabout) and the Body Shop Roundabout as well as between the Station Road Roundabout and A280 Roundabout. Additionally, new cycling and pedestrian facilities will be provided adjacent to but separated from the carriageway.

 

A decision was taken by the Cabinet Member for Highways and Infrastructure (HI25 17/18) in January 2018 in relation to the plans for improvements to the A259 between Worthing and Littlehampton.

Decision:

The Cabinet Member for Highways and Infrastructure has approved:

 

(1)        the investment of additional funding totalling £10,504,000 towards the scheme, with funding sources as set out in Section 2; and

 

(2)        the award of the Phase 2 contract (the construction phase) and agreement of the Contract Target Price to be within the above budget constraints.

 

Interests and Nature of Interests Declared:

None

Publication date: 30/07/2019

Date of decision: 30/07/2019

Effective from: 09/08/2019