Decision details

A2300 Corridor Improvement Scheme - capital allocation HT12 (24/25)

Decision Maker: Cabinet Member for Highways and Transport (Cllr Joy Dennis)

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The A2300 corridor improvement scheme was funded primarily by the Local Growth Fund provided by the Department for Transport with the remaining contributions from the County Council and developers. The completion of the scheme has enabled the commencement of a strategic residential and employment development site to the north of Burgess Hill.

 

The final account for the construction has recently been concluded and it is identified that additional capital funding will be required.

Decision:

The Cabinet Member for Highways and Transport has approved the increase in capital allocation of £0.850m to be funded from the predicted underspend at the final account stage of the A284 Lyminster bypass scheme to enable the conclusion and settlement of the final A2300 account.

 

Interests and Nature of Interests Declared:

None declared

Publication date: 17/10/2024

Date of decision: 17/10/2024

Effective from: 29/10/2024