Decision Maker: Executive Director People Services
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
The Cabinet Member for Adults and Health approved the allocation of funds from ‘Choices for the Future’ capital programme for the first part of the day services rationalization programme (Part A) which is estimated at £2.315m and the commencement of procurement on 1 August 2019.
The Executive Director People Services will award the contract to the successful contractor, to allow for the renovation of Judith Adams, Chichester and The Chestnuts, Bognor Regis Day Centres.
The Executive Director People Services has approved the award of contract to CBG Construction for period of 3 months 26days for value of £1,695,157.01. The contract is to commence on the 2nd December 2019. The expected completion date for the works is 27th March 2020.
None.
Publication date: 24/10/2019
Date of decision: 24/10/2019
Effective from: 05/11/2019
Accompanying Documents: