Endorsement: Budget Increase Eastern Gateway Improvement Project OKD29 20-21

Decision Maker: Executive Director Place Services

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Leader decision LDR04 17.18in September 2017 agreed the scope of the Crawley Growth Programme and, subject to the approval of the Crawley Growth Programme Business Case and the allocation of Local Growth fund (LGF) by the Local Enterprise Partnership (LEP), delegated authority to the then Executive Director of Economy, Infrastructure and Environment to progress projects outlined in the business case.

 

The LEP approved the business case and confirmed an allocation of £14.6m on 21 September 2017. The funding allocations included £8.35m to a project to provide public realm and connectivity improvements at the Eastern Gateway in Crawley.

 

 

Decision:

The Executive Director Place Services has agreed the Design & Build Stage 1 budget increase to £1.32M (an increase of £0.500k) to progress the design and utility enabling works.

Interests and Nature of Interests Declared:

None

 

Publication date: 01/09/2020

Date of decision: 01/09/2020

Effective from: 11/09/2020